As a consequence we plan that: | As a consequence we plan that: | ||
− | * Euler compute nodes, login nodes, and storage systems will be '''off-line from | + | * Euler compute nodes, login nodes, and storage systems will be '''off-line from the morning of Tuesday 26 until and including Friday 29 September'''; we will do out best to bring them back on-line ASAP. |
− | * Batch queues will | + | * Batch queues will remain '''inactive throughout the weekend until Monday 4 October 2017'''. |
The exact times will be coordinated with CSCS and communicated here and by email in the weeks prior to the maintenance. | The exact times will be coordinated with CSCS and communicated here and by email in the weeks prior to the maintenance. |
Revision as of 10:30, 12 September 2017
CSCS informed us that the data centre will be undergoing maintenance on Wednesday 27 and Thursday 28 September 2017, which will require a complete shutdown of Euler.
We will take this opportunity to do some additional maintenance on Euler itself the days before and after the CSCS maintenance. In particular, we will complete the upgrade of Euler to CentOS 7 and prepare for the installation of Euler IV later this year.
As a consequence we plan that:
- Euler compute nodes, login nodes, and storage systems will be off-line from the morning of Tuesday 26 until and including Friday 29 September; we will do out best to bring them back on-line ASAP.
- Batch queues will remain inactive throughout the weekend until Monday 4 October 2017.
The exact times will be coordinated with CSCS and communicated here and by email in the weeks prior to the maintenance.
As usual, batch queues will be progressively inactivated in the days and hours prior to the maintenance, to ensure that no jobs get killed when the cluster is shut down.
Sorry for the inconvenience.